Know your plan
Once the layout and selected finishes are known, list what you need at move-in. Agree which rooms matter first and what can be added later.
Your first-home roadmap
From application and downpayments to keys, defects and renovation. Know what to prepare at each stage, what may be payable and which decisions can wait for your actual flat.
By Home Reno · Published and sources checked
Follow the sequence and use your actual appointment documents for dates. Construction estimates and a neighbour's collection date do not fix the date for your own unit.
01 · Before you apply
Start with your HDB Flat Eligibility (HFE) letter and purchase budget. Keep a separate allowance for renovation, furniture, appliances, moving and a contingency.
Money to plan for
The HFE application is free. The flat application has a $10 administrative fee.
02 · At flat selection
Keep your selected floor plan and the record of any optional components. These are the starting point for deciding what your renovation actually needs.
Money to plan for
The booking option fee is $500 for 2-room Flexi, $1,000 for 3-room and $2,000 for 4-room or larger flats. It forms part of the downpayment.
03 · At Agreement for Lease
Your financing choice, application cohort and any approved scheme determine the schedule. Read your financial plan and appointment documents before committing funds elsewhere.
Money to plan for
Downpayment, stamp duty and legal fees are due as applicable. Use the comparison below as a starting guide.
04 · While construction progresses
Use the waiting period to learn what your household needs. A short brief is easier to improve than a collection of unrelated reference photographs.
Money to plan for
Keep future purchase payments and your renovation savings visible as separate amounts. A renovation price discussed years ahead needs rechecking nearer the work.
05 · When a credible key window is available
Send the same floor plan, selected finishes, priorities and budget to each provider. Ask what can be planned now and what depends on site access.
Money to plan for
Before paying a renovation deposit, check the written contract, payment milestones and terms for changes or delays.
06 · At key collection
Use the actual appointment and handover documents. An estimated completion period is not a confirmed key date for your unit.
Money to plan for
The outstanding purchase amount and applicable fees must be settled using your approved financing arrangements. Keep the renovation budget separate.
07 · Before and during renovation
Coordinate outstanding handover rectification with your renovation provider. Confirm the site measurements, drawings, materials, necessary approvals and written programme.
Money to plan for
Renovation payments follow your contract. HDB purchase instalments do not determine the contractor's payment schedule.
08 · At renovation handover and move-in
Walk through the completed scope, test fittings and record outstanding items with photographs and agreed follow-up. Leave room in the moving plan for cleaning and rectification.
Money to plan for
Check the final account and outstanding work against the contract before settling the remaining renovation payment.
Plan the amounts before the appointment
The percentages below are of the flat purchase price. They show standard payment paths for ordinary long-lease new flats, excluding staggered or deferred arrangements. Loan-to-value is the maximum share funded by the loan, not a promise of the loan you will receive.
The HDB 75% illustration applies from the October 2024 sales exercise. Earlier applications, lower approved loans, short-lease flats and special schemes need their own schedule. Your HDB financial plan and lender's offer take priority.
| Financing path | Agreement for Lease | At completion / key collection | Cash and CPF notes |
|---|---|---|---|
| HDB loan, 75% loan-to-value | 10% | 15% + loan disbursement | Eligible CPF OA and/or cash; booking option fee paid in cash |
| Bank loan, 75% loan-to-value | 20% | 5% + loan disbursement | At signing: at least 5% of price in cash; remaining 15% from eligible CPF OA and/or cash |
| Bank loan, 55% loan-to-value | 20% | 25% + loan disbursement | At signing: at least 10% of price in cash; remaining 10% from eligible CPF OA and/or cash |
| No housing loan | 10% | Remaining 90% | Eligible CPF OA and/or cash, subject to applicable conditions |
On a small screen, swipe across the table to read all four columns.
Count the booking option fee toward the downpayment, not again on top. Keep stamp duty, legal fees and other appointment charges separate. CPF use is subject to applicable conditions. With bank financing, confirm your solicitor's settlement timetable before key collection.
Check HDB's payment table · Check CPF usage conditions · Check the application-cohort basis
Assume the full $300,000 loan is approved and no special downpayment scheme applies. The buyer funds $100,000 of the purchase price in total, subject to eligible CPF and cash arrangements.
This illustration assumes the $2,000 booking option fee is credited toward the $40,000 signing-stage amount, leaving $38,000 to complete that stage. Use HDB's actual payment statement to confirm how the option fee is accounted for in your case. Fees are additional. A smaller actual loan increases what the buyer must fund. This example is an illustration, not an assessment of your eligibility.
The Staggered Downpayment Scheme can reduce the amount due at signing for eligible buyers. Some eligible young couples can also defer their income assessment. The Deferred Downpayment Scheme is a different arrangement for eligible seniors who are right-sizing. These are not the standard rows above: check the scheme and conditions recorded by HDB for your own application.
Read HDB's schemes and eligibility conditionsStart the thinking early. Make commitments against a useful brief and a credible collection window. The stages below are planning recommendations, not HDB deadlines or a guarantee of contractor availability.
A HomeMatch article in CASE's 2024 consumer magazine suggests beginning the search about six months before key collection and choosing a provider about three months before works. Use these as reference points for comparison and design time. Adjust them to your actual key window, scope and provider's programme; they are not a reason to pay under pressure.
Read the planning advice in CASE's magazineOnce the layout and selected finishes are known, list what you need at move-in. Agree which rooms matter first and what can be added later.
When the key window becomes credible, shortlist providers. Send the same information and compare quantities, materials, exclusions and how each quote handles changes.
Check dimensions and the handover condition, coordinate defect rectification, then settle the final scope, approvals and installation programme.
Ask the contract to identify the deposit, later milestones, amounts due and evidence of completion. CaseTrust says accredited renovation businesses collect progressive payments at agreed milestones and cap the initial deposit at 20% of the total cost. That is an accreditation requirement, not a universal 20% payment schedule for every contractor.
Confirm the actual contract terms, written variations and final account. Use the quotation comparison guide and CaseTrust's current protections before committing.
For the on-site sequence and move-in buffer, see how long renovation takes. For scope and permit decisions, use the BTO renovation preparation guide.
First 30 days
HDB's move-in guidance calls for initial defects to be reported within 30 days of key collection and before renovation begins. Inspect promptly so the original condition is documented.
One-year DLP
The HDB Defects Liability Period starts at key collection. The initial reporting window does not mean all coverage ends after 30 days. Report later discoveries promptly within the DLP.
Photograph each issue, record its room and exact location, and keep the reporting reference. Use the Welcome Kit's reporting route or the precinct Building Service Centre (BSC). Agree access and follow-up, then check completed rectification before affected renovation work covers the area.
Avoid promising the renovation start date around an assumed repair duration. If responsibility or sequencing is unclear, ask HDB/BSC and the renovation provider to clarify it before affected work proceeds.
HDB's initial defect reporting guidance · HDB's DLP and rectification routes
No. The standard 75% loan-to-value examples leave at least 25% for the buyer to fund, but the actual loan, application cohort and approved schemes can change your amounts and payment timing. A lower loan means you must provide more. Use your HDB financial plan and lender's offer for your own obligations.
HDB states that the booking option fee forms part of the downpayment. Account for that credit in your financial plan instead of adding the same amount twice. Other fees, such as stamp duty and legal fees, need their own allowance.
Start needs planning once you know your layout and selected finishes. Begin shortlisting when you have a credible key collection window and a useful brief. Confirm quantities, final scope and scheduling after access and site measurement. This is planning guidance, not a compulsory HDB booking deadline.
The HDB Defects Liability Period runs for one year from key collection. HDB's initial reporting guidance calls for defects to be reported within 30 days and before renovation begins. Inspect early, and report later discoveries promptly to HDB or the Building Service Centre within the coverage period.
Coordinate the sequence with the Building Service Centre and renovation provider before affected work starts. Do not let new finishes conceal the issue or obscure the original condition. Rectification timing and whether particular work can proceed depend on the actual defect and agreed sequence.
They are separate records with different responsible parties and start dates. HDB handover defects are reported through HDB or the Building Service Centre. Renovation workmanship follows your contractor's written warranty, and product faults follow the manufacturer's applicable terms.
Explore the published inclusions for your flat size, then send your actual plan, selected finishes and expected key window for an itemised conversation.
Sources checked on 13 November 2026. Recheck current rules when your appointment approaches, especially if your application was made under an earlier scheme. Your individual HDB financial plan, lender's offer and signed renovation contract determine your own obligations.